Building your house in Morocco from abroad: procedures and precautions for Moroccans living abroad

By , architect · Updated on · Reference texts (6)

Key points: A Moroccan living abroad (MRE) can have a house built in Morocco without travelling there: the building permit application may be signed by a duly authorised person (joint order No. 337-20) and is filed online on the Rokhas platform, and an architect registered with the Order is mandatory in urban areas (Law 12-90, article 50). With CITURBAREA, the project is followed remotely: video calls with the architect, drawings, a budget broken down trade by trade and site reports in a shared space; who visits the site, and how often, is written into the contract. (Updated on 19/11/2026, 6 official sources cited below.)

Many Moroccans living abroad build back home without being able to be there. It is possible, provided four points are locked down: the land, the permit, the contracts and the control of the site. Here are the procedures, the texts that apply and the mistakes that cost the most.

In short: a Moroccan living abroad can build without being in Morocco. The building permit application may be signed by the owner, by the design architect or by “any other duly authorised person” (joint order No. 337-20), and it is filed online on Rokhas, mandatory since 2020. In cities, an architect registered with the Order is mandatory (article 50 of Law 12-90). Above 300 m² of covered floor area, the tax administration (DGI) requires an annual return of the construction cost and a solidarity contribution of 60 to 150 dirhams per m². The real risk is not administrative: it is paying for a site that nobody controls.

Your permit, prepared by an architect

A registered architect studies your plot, draws the plans and files your application. First call with no commitment.

Start my file → Estimate my project

📹 Free video call with the architect →

Can you build in Morocco without being there?

Yes. No step requires your permanent physical presence, but some require your signature: the purchase of the land, the architect's contract, the permit information form (with a certified signature) and the works contract. Depending on the case, you sign during a stay in Morocco, at the consulate (signature certification) or through an agent holding a power of attorney. The exact form of the power of attorney depends on the deed: for a property purchase or sale it is more demanding than for filing an application. Check with the consulate and the notary before having it drawn up, and always prefer a special power of attorney, limited to the operation, over a general one.

Step 1: secure the land

Your permit, prepared by an architect

A registered architect studies your plot, draws the plans and files your application. First call with no commitment.

Start my file → Estimate my project

📹 Free video call with the architect →

Step 2: the architect and the building permit

In urban municipalities, delimited centres and their peripheral zones, article 50 of Law 12-90 makes it mandatory to use an architect registered with the Order for any new construction. The architect designs the drawings, prepares the file and submits it. Since April 2020, permit applications go through the Rokhas platform: filing, tracking and decision are all online, which suits an owner living abroad. The detailed steps are in our guides on the building permit procedure and Rokhas, planning permits online.

The file includes in particular the title deed, the ANCFCC (land registry) plan or a topographic survey, the architectural drawings, the architect's contract, the fire safety note and the energy performance note; before the permit is issued, the engineers' structural drawings and the signed information form (joint order No. 337-20). Architect's fees depend on the nature of the project, its complexity and the scope of the assignment. They are set in a contract with the architecture practice. Arc Bati Architecture can propose a fee estimate suited to the project after reviewing its brief. The possible assignments (sketch design, permit, construction documents, specifications, site coordination, follow-up) are described in the guide to architect fees in Morocco.

Step 3: tax, what an MRE needs to know

The tax guide for Moroccans living abroad published by the DGI in 2025 recalls the rule of the social solidarity contribution on self-supplied construction (contribution sociale de solidarité sur les livraisons à soi-même) for a main residence:

Covered floor area of the dwellingContribution
Up to 300 m²Exempt
301 to 400 m²60 dirhams per m²
401 to 500 m²100 dirhams per m²
Above 500 m²150 dirhams per m²

Above 300 m², the contribution applies to the entire covered area. You must also file online, before the end of February each year and until the occupancy permit is issued, an annual return of the construction cost with the list of invoices; the first one must come with an architect's certificate giving the estimated cost of the works, or with the turnkey contract. The contribution is declared and paid within 90 days of the occupancy permit being issued. In practice: keep every invoice, which rules out cash payments without proof. The other taxes are in the guide to building permit fees and taxes.

Step 4: contracts and payments

To compare quotes, see choosing a construction company and the house construction quote example.

Step 5: following the site remotely

The most common failure scenario is well known: money sent in small instalments to a relative or an unsupervised jobbing builder, a site started without approved drawings, defects discovered on return, once the walls are closed. To avoid it, follow-up must be entrusted to a professional independent of the contractor:

  1. visits by the architect at key stages (setting out, reinforcement before concreting, waterproofing, networks before they are closed in);
  2. a dated report with photos after each visit;
  3. approval of each progress statement by the architect before you pay;
  4. handover of the works with signed minutes, listing the snags to be cleared.

What a useful report contains

If you only receive photos sent by the contractor, that is not follow-up: it is communication. The eye must be independent of whoever is being paid.

Time difference and decisions

Set a regular video call, and a response time for site decisions. A choice that waits too long ties up a whole team, and you pay for the delay. Prepare your choice of materials in advance, during a stay or from photographed samples.

With CITURBAREA

The project is followed on the platform: reports and documents in your space, exchanges through the messaging service and by video call with the architect. The content of the follow-up, the number of visits and each party's role in approving progress statements are set in the assignment contract. You can start with a free video call, at a time that suits you among the slots offered, with no commitment.

How much does building cost?

The budget depends on the floor area, the finish level and the city. The 2026 orders of magnitude are in the guide to the cost of building a house per m², and the cost estimator gives you a trade-by-trade estimate for your project in two minutes.

Frequently asked questions

Can a Moroccan living abroad get a building permit without coming to Morocco?

Yes. The application may be signed by the owner, by the design architect or by a duly authorised person (joint order No. 337-20), and the file is submitted online on Rokhas. Some documents do, however, require a certified signature.

Is an architect mandatory to build a house?

In urban municipalities, delimited centres and their peripheral zones, yes: article 50 of Law 12-90 requires an architect registered with the Order for any new construction subject to a permit.

What tax does a Moroccan living abroad pay when building a house?

Up to 300 m² of covered floor area, they are exempt from the social solidarity contribution on self-supplied construction. Above that, they pay 60, 100 or 150 dirhams per m² on the whole area depending on the bracket (DGI tax guide for Moroccans abroad, 2025), on top of municipal taxes.

Do you need to keep the site invoices?

Yes. Above 300 m², the DGI requires an annual return of the construction cost with the list of invoices, until the occupancy permit is obtained.

How do you pay the contractor safely from abroad?

By traceable bank transfers to the company's account, by stages verified and approved by the architect, with a limited advance and a retention until handover.

What power of attorney do you need to build in Morocco?

A special power of attorney, limited to the operation. Its form depends on the deed (purchase, filing the application, signing contracts): check it with the consulate and the notary before having it drawn up.

Reference texts (6)

Start my fileWhatsAppAppeler

Read next

All guides → · Standards library →

Stay informed

Material prices, new planning rules and site advice: one letter a month, written by an architect.

▶ Subscribe to the YouTube channel Channel of architect Yassine AT-TARASSI: sites, prices and procedures on video.
Create my free account →

What next?

  1. Estimate my construction cost →House, villa or apartment building: the cost trade by trade, at dated market prices.
  2. Create my free account →Describe your project and follow your file on CITURBAREA.
  3. Book the free video call with the architect →A video call to review your project, with no commitment.

Our live shows: Tuesday 22:30, Saturday 20:30 (Morocco time). Follow our live shows → · Message CITURBAREA on WhatsApp →

CITURBAREA tools

Free, no account: estimate, compare and decide online, then move forward with the architect.

Create your free account to continue

Supplier prices, technical data sheets and product comparison are reserved for account holders. The account is free and takes a minute.

Create my free account → I already have an account

I am a professional

Ce contenu est consultable uniquement en ligne sur citurbarea.com. هذا المحتوى متاح فقط على الموقع citurbarea.com
Chat with the architectAI Chat