Repairs, extra storey, façade, demolition: which works permit do you need in Morocco?
Redoing a bathroom, adding a storey, opening a window in a façade, knocking down an old house: in Morocco, each of these works falls under a different procedure. Choosing the wrong one exposes you to a stop-work order and a fine.
In short: in Morocco, works on an existing building fall under three regimes. Minor works that touch neither the structure, the façade, the interior layout, the common parts nor the use go through a repair permit (permis de réfection) issued by the commune within 10 working days, with no architect required. Any change affecting those points, and any extra storey (surélévation), requires a building permit (permis de construire) and, in urban areas, an architect registered with the Order. Demolition requires a demolition permit (permis de démolition). Building or altering without authorisation is punished by a fine of 10,000 to 100,000 DH (law 12-90 as amended by law 66-12).
Your permit, prepared by an architect
A registered architect studies your plot, draws the plans and files your application. First call with no commitment.
Which works require a permit?
Law 12-90 (art. 40) requires a building permit for any construction and for changes to existing buildings "if they concern points covered by the regulations". Since the 2016 reform (law 66-12) and its 2019 decrees, it also provides for the repair permit, the regularisation permit and the demolition permit. The general building regulation (règlement général de construction, RGC, decree 2-18-577) divides projects between three procedures.
| Works | Permit | Architect mandatory? |
|---|---|---|
| Minor works with no change of use, not touching the structure, façades, interior layout or jointly owned parts | Repair permit (permis de réfection) | Not required by the texts |
| Seasonal or occasional installation | Repair permit | Not required by the texts |
| Change to a façade (opening, closing, overhang) | Building permit (amending permit, permis modificatif) | Yes in urban areas |
| Interior re-layout, removal of a load-bearing wall, works on common parts | Building permit (amending permit) | Yes in urban areas, with an engineer for the structure |
| Extra storey, extension | Building permit | Yes in urban areas, with an engineer |
| Change of use (dwelling to shop, garage to commercial unit) | Authorisation of the president of the commune after approval by the planning administration (art. 58 of law 12-90) | Depending on the associated works |
| Partial or total demolition | Demolition permit (permis de démolition) | Specialised engineer required in the file |
The text gives no detailed list of "minor works". For routine jobs (tiling, interior painting, like-for-like replacement of windows and doors, boundary wall), practice varies from one commune to another and with the local regulation: check with the planning department before you start. In a medina, a ksar, a kasbah or on a listed or registered building, the procedure is heavier and a certificate from the Culture department may be requested.
How do you get a repair permit?
- Prepare the file (joint order no. 337-20): application signed on the official form, title proving ownership or the right to carry out the works, and where relevant a certificate that the building is neither registered nor listed. One copy is enough.
- File it at the commune's registry office or single window (guichet unique), or on Rokhas. The owner can file personally.
- Review by the commune's planning department, without going through the committee or collecting the opinions of the other administrations: decision within 5 days, issue within 10 working days (RGC, art. 46; Decree 2-18-475, art. 3).
- Carry out the works: put up a visible board (permit number, nature and duration of the works), remove the rubble and clear the public highway at the end.
The repair permit is valid for six months and cannot be renewed (RGC, art. 47). If the works do not start within that period or are not finished within the set duration, a new application must be filed.
Your permit, prepared by an architect
A registered architect studies your plot, draws the plans and files your application. First call with no commitment.
Do you need a permit to add a storey?
Yes. Adding a level is a change that requires a building permit, with an architect and a structural engineer, since the stability of the existing building has to be checked. Three points to check before even drawing:
- Does the zoning plan (plan d'aménagement) allow one more level? Ask for a zoning information certificate (note de renseignements urbanistiques).
- The procedure: adding a storey to a residential building that stays within 15.50 m and R+3 (or 18.50 m and R+4 in a formally accepted subdivision) falls under "small projects", examined in session as soon as the file is filed; beyond that, under "large projects" (RGC, annexes 2 and 3).
- The documents: former approved drawings and initial permit, or failing that a survey of the existing building; drawings in the conventional colours (existing in neutral, to be built in red, to be demolished in yellow).
An unauthorised extra storey also blocks the building's occupancy permit (permis d'habiter). To budget for the additional floor, use our free cost estimator.
How do you get a demolition permit?
The demolition permit is issued by the president of the commune within one month (art. 63-1 of law 12-90; decree 2-18-475, art. 14). The file, filed in a single copy since joint order no. 1032-21 (BO no. 6992 of 3 June 2021), which amended order 337-20, includes: application, title deed, contract with a specialised demolition company, contract with a specialised engineer, photos of the building and of the neighbouring buildings, a work schedule, and a technical study by the engineer (diagnosis, method, safety measures for neighbouring buildings). Order 337-20 exempts a detached single-family house no more than 8 metres high, but article 13 of decree 2-18-475 presents the technical study as mandatory without exception: to be safe, provide it in every case. The permit sets a deadline for carrying out the works; the official template provides that it lapses after six months if works have not started, and requires a site fence, a board, and notice to the commune at least 15 working days before the demolition begins.
What are the risks of works without a permit?
Law 66-12 tightened the controls and penalties of law 12-90. When a violation is recorded by an authorised officer:
- Immediate stop of the works, with possible seizure of equipment and sealing of the site if the order is not respected.
- Formal notice, when the violation is not serious, to take the necessary measures to end it within 10 days to one month (art. 68): this means bringing the works into compliance, not an administrative regularisation.
- Demolition order by the local administrative authority if nothing is done; if it is not carried out, demolition by an administrative committee chaired by the wali or the governor, within 48 hours, at the offender's expense (art. 68). For a building without a permit on public land or in a zone where building is not allowed, the local authority demolishes directly of its own motion (art. 70).
- Criminal prosecution and fines.
| Violation | Penalty |
|---|---|
| Building, or altering an existing building, without a permit | Fine of 10,000 to 100,000 DH; imprisonment for a repeat offence |
| Occupying, as the owner, a building without an occupancy permit or certificate of compliance | Fine of 2,000 to 10,000 DH (art. 75) |
| Making that building available to third parties without an occupancy permit or certificate of compliance | Fine of 10,000 to 100,000 DH (art. 75) |
| Not complying with the permit (height, volumes, siting, floor area, use) | Fine of 10,000 to 50,000 DH (art. 72) |
| Adding one or more unauthorised storeys | Imprisonment of one to three months and/or fine of 50,000 to 100,000 DH (art. 72) |
| Changing a façade without a permit | Fine of 2,000 to 20,000 DH (art. 73) |
| Building in a zone where building is not allowed | Fine of 10,000 to 100,000 DH (art. 71); demolition of the authority's own motion (art. 70) |
| Building without authorisation on public or private land of the State or local authorities, or on collective land | Fine of 100,000 to 200,000 DH (art. 77); demolition of the authority's own motion (art. 70) |
The project owner is not the only one at risk: the contractor, the architect, the engineer or the surveyor can be prosecuted as co-offenders, in particular if they do not report the violation within 48 hours. That is why a serious architect will refuse to supervise a site that departs from the approved drawings.
Can works already carried out be regularised?
The regularisation permit (permis de régularisation) (decree 2-18-475) makes it possible to regularise a non-compliant building that meets safety, stability and planning rules; it stands in for the occupancy permit. The window for filing applications, opened for two years in 2019-2020, was reopened for two years by decree 2-23-103, published in May 2023. That window appears to have been closed since May 2025: no extension has been found to date. Check with your commune whether an application can still be accepted before taking any step. Outside this scheme, the only route is bringing the building into compliance, or even demolishing the illegal part.
When should you call in an architect?
As soon as the works touch the structure, the façade, the layout or the common parts, or add floor area: article 50 of law 12-90 makes an architect registered with the Order mandatory for any change subject to a building permit in urban areas. Even for a repair, the architect's advice avoids filing under the wrong procedure. See our guides on architect fees, the building permit and the fees and taxes.
CITURBAREA, an architect's practice registered with the Order and based in Kénitra, studies the feasibility of your extra-storey, renovation or demolition-and-rebuild works in the Rabat-Salé-Kénitra region. Describe your project to us.
Frequently asked questions
Do you need a permit for repair works in Morocco?
Yes, minor works on an existing building fall under the repair permit (permis de réfection), issued by the commune within 10 working days. If the works touch the structure, the façade, the interior layout, the common parts or the use, a building permit is required. For small jobs, practice varies from one commune to another: check before you start.
How long is a repair permit valid?
Six months from its issue, and it cannot be renewed (article 47 of the general building regulation). If the works are not carried out within that period, a new application is needed.
Do you need an architect to add a storey in Morocco?
Yes in urban communes, delimited centres and their peripheral zones: an extra storey requires a building permit, and article 50 of law 12-90 makes it mandatory there to use an architect registered with the Order and specialised engineers.
Do you need a permit to change a façade?
Yes. A change to a façade is not a minor work within the meaning of the general building regulation: it falls under the building permit. Any change to a façade without a permit is penalised under law 66-12.
What is the fine for building without a permit in Morocco?
Building, or altering an existing building, without a permit is punished by a fine of 10,000 to 100,000 DH, with possible imprisonment for a repeat offence, on top of the stop-work order and a possible demolition order.
Do you need a permit to demolish a house?
Yes, a demolition permit issued by the president of the commune. The file includes in particular a contract with a demolition company and a specialised engineer, and a technical study (order 337-20 exempts a detached single-family house no more than 8 metres high, but decree 2-18-475 presents it as mandatory: better to provide it). The file is filed in a single copy (order 1032-21) and the permit is issued within one month.
Can a building built without a permit be regularised?
The regularisation permit (decree 2-18-475) allows it, subject to safety and planning conditions, during filing periods set by decree. The last known window, reopened for two years by decree 2-23-103 of May 2023, appears to have closed in May 2025, with no extension found: check with your commune whether the scheme is still open.
What is the fine for occupying a house without an occupancy permit?
An owner who occupies a building personally without an occupancy permit or certificate of compliance faces a fine of 2,000 to 10,000 DH. If the owner makes it available to third parties (rental, loan), the fine is 10,000 to 100,000 DH (article 75 of law 12-90, as worded by law 66-12).
Reference texts (10)
- Loi n° 12-90 relative à l'urbanisme, texte diffusé par l'Ordre des architectes
- Loi n° 66-12 relative au contrôle et à la répression des infractions en matière d'urbanisme et de construction (dahir n° 1-16-124 du 25 août 2016)
- Décret n° 2-18-577 (règlement général de construction, annexes 2 à 4 et 7) et arrêté conjoint n° 337-20 fixant les pièces des dossiers — BO n° 6874 du 16 avril 2020
- Guide pratique de la loi n° 66-12 (en arabe), Maroclaw
- La Vie Éco — Une loi pour mettre fin à la pagaille des chantiers de construction (loi 66-12)
- CasablancaCity.ma — Permis de réfection, de démolition et de régularisation sur Rokhas (mai 2020)
- Le360 — Constructions non réglementaires : un nouveau délai de 2 ans pour la régularisation (décret 2-23-103)
- Loi n° 66-12 — traduction française au BO n° 6770 du 18 avril 2019 (art. 40, 63-1 et 64 à 80-1 de la loi 12-90), copie publiée par l'Agence urbaine de Kénitra-Sidi Kacem
- Arrêté conjoint n° 1032-21 du 13 avril 2021 modifiant l'arrêté conjoint n° 337-20 (dossiers en un seul exemplaire) — BO n° 6992 du 3 juin 2021
- Décret n° 2-18-475 (permis de réfection, de régularisation et de démolition), version consolidée avec le décret n° 2-23-103 du 8 mai 2023 — AUKS